School Low Voltage Systems at Washington Market School
- Phased around the school day
- Lighting and PA control
- With SPK/Lewis
Lighting controls and a public address system, installed in phases so the school kept running.
- 1,000+
installations over 10+ years
- 24/7
support for managed-service clients
- Excellent
Rated 4.9/5 by 110+ NYC corporations
- 7 Active Teams
Operating throughout New York
Project at a glance
Highline Integrated Security delivered school low voltage systems at Washington Market School in 2025, engaged by the general contractor SPK/Lewis.
- Client and sector
- Washington Market School · K-12 education
- Location
- Tribeca, Manhattan
- Building type
- Existing school building, in use throughout the works
- Engaged by
- SPK/Lewis (general contractor)
- Scope
- Infrastructure assessment, automated lighting controls, public address system, phased installation
- Platforms
- Cooper (lighting controls) · AtlasIED (public address)
- Year
- 2025
The challenge: new systems in a school that stayed open
The challenge was to add two building-wide low voltage systems while daily operations and communication carried on.
An existing building
Pathways and capacity had to be verified on site before an installation sequence could be set.
Daily operations
Staff and students used the building every day, so no area could be left mid-installation.
The GC's program
Low voltage work had to fit SPK/Lewis's construction sequence alongside the other trades.
Shared routes
Lighting controls and PA share ceilings and pathways, so their work was sequenced together.
Our approach: assess, phase, commission
We assessed the building first, then phased the work so each area was finished and handed back before the next began.
- 01
Assess the existing infrastructure
We surveyed the existing low voltage infrastructure, so the plan matched what was in the ceilings.
- 02
Plan the phases with the GC
We set the sequence inside SPK/Lewis's program, so each phase finished while the rest of the school operated.
- 03
Install the lighting controls
We installed Cooper automated low voltage lighting controls.
- 04
Install the public address system
We installed an AtlasIED PA to carry announcements across the facility.
- 05
Commission each phase before moving on
Every phase ended with tested, working systems, so the school never relied on a half-finished installation.
One team owned the assessment, phasing and both systems, so SPK/Lewis had one point of contact. Every system we install is backed by a 12-month warranty.
What we installed
The low voltage scope covered two systems, delivered as one coordinated package.
| System | Platform | What it does for the school |
|---|---|---|
| Automated lighting controls | Cooper | Automates lighting control across the building and simplifies daily operation |
| Public address system | AtlasIED | Carries announcements across the whole school from one point |
The result
Washington Market School gained facility-wide announcements and automated lighting without closing.
Facility-wide announcements
The AtlasIED PA reaches the whole school from one point.
Operational efficiency
Automated lighting controls simplified daily building operation.
No shutdown
The phased program kept the school running for the length of the project.
Request a site assessment (on-site or virtual) · Call 917-473-8077
Planning low voltage systems for a school renovation
Low voltage decisions made during a school renovation set what the building can add later.
Pathway capacity for future systems
Size pathways and closets now for access control, cameras and intercom, so ceilings do not have to be reopened.
Plenum-rated cable where required
Air-handling ceilings in NYC commercial buildings often require plenum-rated cable.
Testing and as-builts at each handover
Ask for tested, labeled cabling and as-built documentation at the end of every phase, not only at project close.
NDAA checks on funded projects
If federal funds are involved, check camera and video equipment against NDAA Section 889 before anything is specified.
Related services
The services and projects closest to a phased school renovation.
- Structured cabling and low voltage (→ /structured-cabling-nyc/)
- Security systems for schools and campuses (→ /school-security-systems-nyc/)
- Construction and development projects (→ /construction-security-nyc/)
- Commercial security systems in Manhattan (→ /security-system-installation-manhattan/)
- K-12 access control at Lexington School for the Deaf (→ /case-study/k12-access-control-and-accessibility-lexington-school-for-the-deaf)
FAQs
School low voltage systems: FAQs
Short answers on the systems, working in an open school, the GC role and handover.
Which school low voltage systems did Highline install at Washington Market School?
The school low voltage systems Highline installed at Washington Market School were Cooper automated lighting controls and an AtlasIED public address system. Both went in through a phased program with SPK/Lewis.
Can low voltage work happen while a school is open?
Low voltage work can happen while a school is open when it is phased. Each area is completed, tested and handed back before the next begins, so the rest of the building keeps running.
Does Highline act as the low voltage contractor on NYC school projects?
Highline acts as the low voltage partner on NYC school projects, often engaged by the general contractor, as SPK/Lewis did here. We fit our sequence to the GC's program and coordinate with the other trades.
Can PA and lighting controls integrate with security systems later?
PA and lighting controls can integrate with security systems later if the infrastructure is planned for it. Designing pathways and capacity now avoids reopening ceilings for future access control or cameras.
What should a school ask for at handover?
At handover, a school should ask for tested systems, labeled cabling and as-built documentation for each phase. Those records make later additions faster.
Renovating a school or institutional building?
Bring us in early so low voltage is sequenced with the rest of the work.